Scope :
Project Cost :
Contractor :
Size :
Started on :
Current Status :
|
|
|
Dh. Hulhudheli
Scope : Harbour basin and infrastruture
Project Cost : MRF 16,468,711.70
Contractor : MTCC
Size : 300 x 200 ft
Started on : Friday, October 19, 2007
Current Status :
Dredging : 100%
Seawall : 100%
Quay wall : 100%
Works completed on 9th October 2008
|
|
|
Gdh.Nadalla
Scope : Harbor basin+ infrastructure
Project Cost : MRf. 15,812,547.28
Contractor : MTCC
Size : 300 x 200 ft
Started on : Wednesday, August 08, 2007
Current Status :
Dredging : 100%
Seawall : 100%
Quay wall : 100%
98% of total wprks completed. Expected completion date 4th October 2008. 92% of rock boulders revetment works completed.
|
|
|
H Dh. Finey
Scope : Harbour basin and infrastructure
Project Cost : 15,272,182.71
Contractor : MTCC
Size : 200ft X 300ft
Started on : Monday, April 14, 2008
Current Status :
Dredging : 100%
Seawall : 85%
61% of total works completed. Expected completion date is 14th December 2008
|
|
|
H Dh. Navaidhoo
Scope : Harbour basin and infrastruture
Project Cost : Mrf 8,606,340.89
Contractor : MTCC
Size : 300 x 200 ft
Started on : Thursday, August 23, 2007
Current Status :
Dredging : 100%
Seawall : 100%
Quay wall : 100%
100% works completed.
|
|
|
H.Dh Kumundhoo
Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,293,680.52
Contractor : Heavy Load Maldives Pvt. Ltd
Size : 300ft x 200ft
Started on : Saturday, March 01, 2008
Current Status :
Dredging : 10%
Seawall : 0%
Quay wall : 0%
Q-wall and breakwater finaliza
|
|
|
Ha. Maarandhoo
Scope : Harbour basin and infrastructure
Project Cost : 21,493,954.17
Contractor : MTCC
Size : 200ft X 300ft
Started on : Sunday, June 01, 2008
Current Status :
Dredging : 70%
Quay wall : 33%
28% of total works completed. Expected completion date is 29th January 2009
|
|
|
HA. Thakandhoo
Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,351,491.52
Contractor : RKL Group Pvt. Ltd.
Size : 300ft x 200ft
Started on : Monday, March 10, 2008
Current Status :
Dredging : 10%
Seawall : 0%
Quay wall : 0%
Q-wall and breakwater finaliza
|
|
|
HA. Uligamu
Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,351,491.52
Contractor : RKL Group Pvt. Ltd.
Size : 300ft x 200ft
Started on : Monday, March 10, 2008
Current Status :
Dredging : 10%
Seawall : 0%
Quay wall : 0%
Q-wall and breakwater finaliza
|
|
|
L. Gan Mukurimagu
Scope : Harbour basin and infrastruture
Project Cost : 21,096,854.33
Contractor : MTCC
Size : 200ft X 300ft
Started on : Wednesday, July 16, 2008
Current Status :
Works started on 17th September 2008. Team mobilised on 25th July 2008
|
|
|
L. Kunahandhoo
Scope : Channel dredging and harbour i
Project Cost : MRf 6,898,059.66
Contractor : MTCC
Size : 300 x 200 ft
Started on : Thursday, February 01, 2007
Current Status :
Dredging : 80%
Quay wall : 29%
Project stopped due to contrac
|
|
|
L. Mundoo
Scope : Harbour basin and infrastructure
Project Cost : 17,685,654.26
Contractor : MTCC
Size : 200ft X 300ft
Started on : Friday, July 11, 2008
Current Status :
22% of total works completed. Expected completion date is 6th January 2009
|
|
|
Lh. Olhuvelifushi
Scope : Harbour basin and infrastruture
Project Cost : 15,038,835.66
Contractor : MTCC
Size : 300 x 200 ft
Started on : Sunday, April 20, 2008
Current Status :
Dredging : 98%
Seawall : 00%
Quay wall : 00%
33% of total works completed. Expected completion date is 10th Novemeber 2008
|
|
|
N. Landhoo
Scope : Harbour basin dredging and Inf
Project Cost : MRF 21,288,222.80
Contractor : MTCC
Size : 300ft x 200ft
Started on : Thursday, March 13, 2008
Current Status :
Dredging : 100%
Seawall : 00%
Quay wall : 82%
62% of total works completed. Expected completion date is 10th November 2008
|
|
|
R. Angolhitheemu
Scope : Harbour basin and infrastruture
Project Cost : Mrf 9,897,765.27
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :
Current Status :
Contractor mobilised to site o
|
|
|
R. Innamaadhoo
Scope : Dredging + Harbour Infrastruct
Project Cost : Mrf 1,869,450.00+1,138,154 (ad
Contractor : MTCC
Size : --
Started on :
Current Status :
Dredging : 100%
Seawall : 99%
Quay wall : 100%
Assigned works completed; proj
|
|
|
R. Kinolhas
Scope : Harbour basin and infrastruture
Project Cost : Mrf 9,897,765.27
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :
Current Status :
Bathymetry and detail design w
|
|
|
R. Vaadhoo
Scope : Harbour basin and infrastruture
Project Cost : 16,440,218.42
Contractor : MTCC
Size : 200ft X 300ft
Started on : Tuesday, September 16, 2008
Current Status :
19% of total works completed. Expected completion date is 11th February 2009
|
|
|
Sh. Bilehafahi
Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,109,435.58
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :
Current Status :
Bathymetry and detail design w
|
|
|
Sh. Goidhoo
Scope : Harbour basin and infrastructure
Project Cost : 21,721,016.47
Contractor : MTCC
Size : 200ft X 300ft
Started on : Saturday, July 05, 2008
Current Status :
45% of total works completed. Expected completed date is 21st January 2009
|
|
|
Sh. Narudhoo
Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,109,435.58
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :
Current Status :
EIA works ongoing
|
|
|
AA. Rasdhoo
Scope : Harbour basin and infrastruture
Project Cost : Mrf 14,694,931.92
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
Dredging : 0%
Seawall : 0%
Quay wall : 0%
Revetment : 0%
EIA & detail design works in p
|
|
|
G.A. Nilandhoo
Scope : Harbour basin dredging and Inf
Project Cost : MRF 17.0 Million
Contractor : Boppana Civil Construction Pte
Size : 600x250ft
Started on : Thursday, March 01, 2007
Current Status :
Dredging : 90%
Seawall : 0%
Quay wall : 0%
Revetment : 0%
Contract Terminated on 11th Ma
|
|
|
GA Villingili
Scope : Reclamation and coastal infrastructure
Project Cost : € 17,632,600
Contractor : Boskalis International B.V
Size :
Started on : Wednesday, August 01, 2007
Current Status :
Reclamation 100% completed
|
|
|
H.Dh Kulhudhhfushi phase 1
Scope : Harbour basin and infrastruture
Project Cost : MRF 42,002,348.97
Contractor : MTCC
Size :
Started on : Tuesday, December 25, 2007
Current Status :
Dredging : 0%
Seawall : 0%
Quay wall : 0%
Revetment : 0%
Contractor mobilized
|
|
|
K. Maafushi
Scope : Harbour basin and infrastruture
Project Cost : MRF 30,213,673.25
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA & detail design works in p
|
|
|
L. Maamendhoo
Scope : Harbour basin and infrastruture
Project Cost : MRF 35,449,780.26
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA in progress.
Detail desi
|
|
|
M. Mulah
Scope : Harbour + Harbour Infrastructure
Project Cost : Mrf 27.9 million
Contractor : Boppana constructions (india)
Size : 750ft X 250ft
Started on : Tuesday, June 19, 2007
Current Status :
Dredging : 90%
Seawall : 0%
Quay wall : 0%
Revetment : 0%
Dredging works in progress
|
|
|
N. Kendhikulhudhoo
Scope : Harbour basin and infrastruture
Project Cost : MRF 35,734,088.78
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA & detail design works in p
|
|
|
R. Hulhudhuffaaru
Scope : Harbour + Harbour Infrastructure
Project Cost : MRf 21,065,663.54
Contractor : MTCC
Size : 700ft X 250Ft
Started on : Monday, July 16, 2007
Current Status :
Dredging : 100%
Seawall : 100%
Quay wall : 100%
100% works completed on 10th September 2008
|
|
|
R. Maakurathu
Scope : Harbour basin and infrastruture
Project Cost : MRF 27,257,885.53
Contractor : AMIN Construction Company Pvt.
Size : 153m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA & detail design works in p
|
|
|
Sh. Milandhoo
Scope : Harbour basin and infrastruture
Project Cost : MRF 34,249,001.05
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA & detail design works in p
|
|
|
Th. Veymandoo
Scope : Harbour basin and infrastruture
Project Cost : MRF 45,265,728.90
Contractor : AMIN Construction Company Pvt.
Size : 366m x 76.2m
Started on : Monday, February 04, 2008
Current Status :
EIA works in progress.
Detail
|
|
|
A.Dh. Mahibadhoo Phase 1
Scope : Harbour Basin + Quaywall
Project Cost :
Contractor : Maldives Transport and Contracting Company
Size : 228m x 76m
Started on : Sunday, November 04, 2007
Current Status :
Dredging : 100%
Seawall : 0%
Quay wall : 32%
Contract awarded to MTCC to finish the remaining works. Contract signed on 6th October 2008
|
|
|
B . Hithaadhoo Phase 1
Scope : Reconstruction of quaywall
Project Cost : MRF 6,106,042.76
Contractor : Nexsar Company Pvt Ltd
Size : 372m Quaywall
Started on :
Current Status :
capping beam works ongoing. corner block casted
|
|
|
Dh. Bandidhoo
Scope : Quaywall and Dredging of habour basin
Project Cost : Mrf 8,447,215.65
Contractor : Umet Construction Pvt Ltd
Size : 283m / 16816.80m3
Started on : Tuesday, July 22, 2008
Current Status :
Dredging : 75%
Quay wall : 0%
First shipment of blocks on the way to site
|
|
|
Dh. Kudahuvadhoo Phase 2
Scope : Harbour extension and additional infrastructure
Project Cost : Mrf 8,992,456.08
Contractor : AIMA Construction Company Pvt.
Size : 242m
Started on :
Current Status :
Dredging : 99%
Quay wall : 100%
Project completion date due on 13th September 2008
|
|
|
R.Alifushi
Scope : Habour Basin and Infrastructure
Project Cost : Mrf 40,991,424.73
Contractor : Maldives Transport and Contracting Company
Size :
Started on :
Current Status :
Dredging : 0%
Seawall : 0%
Quay wall : 0%
Contract signed on 29th September 2008 between MCPI and MTCC
|
|
|
R.Dhuvaafaru
Scope : Habour Basin and Infrastructure
Project Cost : USD 5,442,925.85
Contractor : Aima Construction Company Pvt Ltd
Size : 1200 x 250
Started on :
Current Status :
Dredging : 0%
Seawall : 0%
Quay wall : 0%
Revetment : 0%
Contractor mobilizing on site
|
|
|
R.Meedhoo
Scope : Habour Basin and Infrastructure
Project Cost : Mrf 29,722,803.86
Contractor : Maldives Transport and Contracting Company
Size : 228m X 75m
Started on :
Current Status :
Dredging : 0%
Seawall : 0%
Quay wall : 0%
Contract signed in on 29th September 2008 between MCPI and MTCC
|
|
|
S. Maradhoo
Scope : Harbour basin and infrastruture
Project Cost : MRf 29,439,536.00
Contractor : MTHojgaard
Size : 182m x 91m
Started on : Thursday, September 20, 2007
Current Status :
Dredging : 90%
Seawall : 45%
Quay wall : 70%
Quay wall blocks casting works completed
|
|