H.Dh Kumundhoo

H.Dh Kumundhoo

Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,293,680.52
Contractor : Heavy Load Maldives Pvt. Ltd
Size : 300ft x 250ft
Started on : Saturday, March 01, 2008


Current Status :

    Dredging : 50%
    Seawall : 0%
    Quay wall : 10%
Harbour extension works ongoing. QW units supply ongoing.


HA. Thakandhoo

HA. Thakandhoo

Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,351,491.52
Contractor : RKL Group Pvt. Ltd.
Size : 300ft x 200ft
Started on : Monday, March 10, 2008


Current Status :

    Dredging : 100%
    Seawall : 30%
    Quay wall : 50%
QW installation ongoing


HA. Uligamu

HA. Uligamu

Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,351,491.52
Contractor : RKL Group Pvt. Ltd.
Size : 300ft x 200ft
Started on : Monday, March 10, 2008


Current Status :

    Dredging : 90%
    Seawall : 10%
    Quay wall : 50%
QW capping beam works ongoing


L. Gan Mukurimagu

L. Gan Mukurimagu

Scope : Harbour basin and infrastruture
Project Cost : 21,096,854.33
Contractor : MTCC
Size : 500ft X 300ft
Started on : Wednesday, July 16, 2008


Current Status :

    Dredging : 90%
    Seawall : 10%
Works started on 17th September 2008. Team mobilised on 25th July 2008. 10% of total work completed.


L. Kunahandhoo

L. Kunahandhoo

Scope : Channel dredging and harbour i
Project Cost : MRf 6,898,059.66
Contractor : MTCC
Size : 300 x 200 ft
Started on : Thursday, February 01, 2007


Current Status :

    Dredging : 80%
    Quay wall : 29%
Project stopped due to vandalization of contractor's equipment.


L. Mundoo

L. Mundoo

Scope : Harbour basin and infrastructure
Project Cost : 17,685,654.26
Contractor : MTCC
Size : 200ft X 300ft
Started on : Friday, July 11, 2008


Current Status :

    Dredging : 100%
    Seawall : 50%
    Quay wall : 50%


Lh. Olhuvelifushi

Lh. Olhuvelifushi

Scope : Harbour basin and infrastruture
Project Cost : 15,038,835.66
Contractor : MTCC
Size : 300 x 200 ft
Started on : Sunday, April 20, 2008


Current Status :

    Dredging : 100%
    Seawall : 0%
    Quay wall : 100%


R. Angolhitheemu

R. Angolhitheemu

Scope : Harbour basin and infrastruture
Project Cost : Mrf 9,897,765.27
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :


Current Status :

    Dredging : 90%
Contractor mobilised to site o


R. Kinolhas

R. Kinolhas

Scope : Harbour basin and infrastruture
Project Cost : Mrf 9,897,765.27
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :


Current Status :

Bathymetry and detail design w


R. Vaadhoo

R. Vaadhoo

Scope : Harbour basin and infrastruture
Project Cost : 16,440,218.42
Contractor : MTCC
Size : 200ft X 300ft
Started on : Tuesday, September 16, 2008


Current Status :

    Dredging : 100%
95% of total works completed. Expected completion date is 15th May 2009


Sh. Bilehafahi

Sh. Bilehafahi

Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,109,435.58
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :


Current Status :

Bathymetry and detail design w


Sh. Goidhoo

Sh. Goidhoo

Scope : Harbour basin and infrastructure
Project Cost : 21,721,016.47
Contractor : MTCC
Size : 200ft X 300ft
Started on : Saturday, July 05, 2008


Current Status :

    Dredging : 100%
    Seawall : 55%
51% of total works completed. Expected completed date is 21st January 2009


Sh. Narudhoo

Sh. Narudhoo

Scope : Harbour basin and infrastruture
Project Cost : Mrf 10,109,435.58
Contractor : Aima Construction Company Pvt.
Size : 300ft x 200ft
Started on :


Current Status :

EIA works ongoing


AA. Rasdhoo

AA. Rasdhoo

Scope : Harbour basin and infrastruture
Project Cost : Mrf 14,694,931.92
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on :


Current Status :

    Dredging : 0%
    Seawall : 0%
    Quay wall : 0%
    Revetment : 0%
EIA 20% completed


G.A. Nilandhoo

G.A. Nilandhoo

Scope : Harbour basin dredging and Inf
Project Cost : MRF 45,614,812.24
Contractor : Boppana Civil Construction Pte
Size : 600x250ft
Started on : Tuesday, November 11, 2008


Current Status :

    Dredging : 96%
    Seawall : 0%
    Quay wall : 21%
    Revetment : 0%
Contract Terminated on 11th Ma


H.Dh Kulhudhhfushi phase 1

H.Dh Kulhudhhfushi phase 1

Scope : Harbour basin and infrastruture
Project Cost : MRF 42,002,348.97
Contractor : MTCC
Size :
Started on : Tuesday, December 25, 2007


Current Status :

    Dredging : 85%
    Seawall : 44%
    Quay wall : 19%
    Revetment : 0%
Contractor mobilized


K. Maafushi

K. Maafushi

Scope : Harbour basin and infrastruture
Project Cost : MRF 30,213,673.25
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Monday, February 04, 2008


Current Status :

    Dredging : 3%%
4.18% completed. EIA completed


L. Maamendhoo

L. Maamendhoo

Scope : Harbour basin and infrastruture
Project Cost : MRF 35,449,780.26
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Friday, May 30, 2008


Current Status :

    Dredging : 100%
    Seawall : 100%
    Quay wall : 100%
    Revetment : 57%
EIA in progress. Detail desi


M. Mulah

M. Mulah

Scope : Harbour + Harbour Infrastructure
Project Cost : Mrf 21,172,652.22
Contractor : PWS
Size : 750ft X 250ft
Started on : Monday, November 10, 2008


Current Status :

    Dredging : 100%
    Seawall : 100%
    Quay wall : 100%
    Revetment : 86%
Dredging works in progress


N. Kendhikulhudhoo

N. Kendhikulhudhoo

Scope : Harbour basin and infrastruture
Project Cost : MRF 35,734,088.78
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on : Saturday, September 13, 2008


Current Status :

    Dredging : 60%
    Seawall : 52%
12.33% completed. EIA & detailed design works completed


R. Maakurathu

R. Maakurathu

Scope : Harbour basin and infrastruture
Project Cost : MRF 27,257,885.53
Contractor : AMIN Construction Company Pvt.
Size : 153m x 76.2m
Started on : Friday, March 07, 2008


Current Status :

    Dredging : 41%
EIA & detail design works completed


Sh. Milandhoo

Sh. Milandhoo

Scope : Harbour basin and infrastruture
Project Cost : MRF 34,249,001.05
Contractor : AMIN Construction Company Pvt.
Size : 229m x 76.2m
Started on :


Current Status :

EIA 70% completed


Th. Veymandoo

Th. Veymandoo

Scope : Harbour basin and infrastruture
Project Cost : MRF 45,265,728.90
Contractor : AMIN Construction Company Pvt.
Size : 366m x 76.2m
Started on : Saturday, May 31, 2008


Current Status :

    Dredging : 100%
    Seawall : 100%
    Quay wall : 98%
    Revetment : 51%
EIA works in progress. Detail


A.Dh. Mahibadhoo  Phase 1

A.Dh. Mahibadhoo Phase 1

Scope : Harbour Basin + Quaywall
Project Cost : Mrf. 20,104742.22
Contractor : Maldives Transport and Contracting Company
Size : 228m x 76m
Started on : Monday, November 10, 2008


Current Status :

    Dredging : 100%
    Seawall : 18%
    Quay wall : 75%
Contract awarded to MTCC to finish the remaining works. Contract signed on 6th October 2008


B .  Hithaadhoo Phase 1

B . Hithaadhoo Phase 1

Scope : Reconstruction of quaywall
Project Cost : MRF 6,106,042.76
Contractor : Nexsar Company Pvt Ltd
Size : 372m Quaywall
Started on : Monday, March 24, 2008


Current Status :

    Dredging : 0%
    Quay wall : 45%
[worked stopped at the site due to quay wall block shortage. 186m of capping beam completed. 211m quay wall construction works completed.]


Dh. Bandidhoo

Dh. Bandidhoo

Scope : Quaywall and Dredging of habour basin
Project Cost : Mrf 8,447,215.65
Contractor : Umet Construction Pvt Ltd
Size : 283m / 16816.80m3
Started on : Tuesday, July 22, 2008


Current Status :

    Dredging : 100%
    Seawall : 00%
    Quay wall : 70%
First shipment of blocks on the way to site


Dh. Kudahuvadhoo Phase 2

Dh. Kudahuvadhoo Phase 2

Scope : Harbour extension and additional infrastructure
Project Cost : Mrf 8,992,456.08
Contractor : AIMA Construction Company Pvt.Ltd.
Size : 242m
Started on : Tuesday, January 29, 2008


Current Status :

    Dredging : 100%
    Quay wall : 100%
Project completion date due on 13th September 2008


Dh.kudahuvadhoo phase1

Dh.kudahuvadhoo phase1

Scope : Quaywall and harbour basin dragin
Project Cost : 5,634,583.97
Contractor :
Size :
Started on : Sunday, June 24, 2007


Current Status :

    Quay wall : 100%


R.Alifushi

R.Alifushi

Scope : Habour Basin and Infrastructure
Project Cost : Mrf 40,991,424.73
Contractor : Maldives Transport and Contracting Company
Size : 229m x 76m
Started on : Monday, October 20, 2008


Current Status :

    Dredging : 100%
    Seawall : 25%
    Quay wall : 0%
Contract signed on 29th September 2008 between MCPI and MTCC


R.Dhuvaafaru

R.Dhuvaafaru

Scope : Habour Basin and Infrastructure
Project Cost : USD 5,442,925.85
Contractor : Aima Construction Company Pvt Ltd
Size : 1200 x 250
Started on : Monday, July 14, 2008


Current Status :

    Dredging : 00%
    Seawall : 0%
    Quay wall : 00%
    Revetment : 0%
[Dredging started at the site. Survey to commence break water in progress]


R.Meedhoo

R.Meedhoo

Scope : Habour Basin and Infrastructure
Project Cost : Mrf 29,722,803.86
Contractor : Maldives Transport and Contracting Company
Size : 228m X 75m
Started on : Monday, September 29, 2008


Current Status :

    Dredging : 0%
    Seawall : 0%
    Quay wall : 75%
42% of the total contract has been completed. Contract signed in on 29th September 2008 between MCPI and MTCC


S. Maradhoo

S. Maradhoo

Scope : Harbour basin and infrastruture
Project Cost : MRf 29,439,536.00
Contractor : MTHojgaard
Size : 182m x 91m
Started on : Friday, June 15, 2007


Current Status :

    Dredging : 100%
    Seawall : 98%
    Quay wall : 100%
Quay wall blocks casting works completed






Copyright © 2008, Ministry of Housing, Transport and Environment. All Rights Reserved.
Ameenee Magu, Maafannu, Male', 20392, Republic of Maldives.
Tel: +(960) 300 4300, Fax: +(960) 300 4301, Email: secretariat@mhte.gov.mv